Actions
Activity #501
closedDeployement activity on Bajaj on prem
Start date:
11/13/2024
Due date:
02/21/2025
% Done:
0%
Estimated time:
End Date:
02/21/2025
Description
Deployement activity on Bajaj on prem
Updated by Sanket Mohite 5 months ago
Sanket Mohite wrote:
Deployement activity on Bajaj on prem
refer email RE: Assistance Required: Error Encountered During Rubiscape Deployment on Instance BALAKPOCTEST
Updated by Sanket Mohite about 2 months ago
- Due date set to 02/21/2025
- Status changed from New to closed
- End Date set to 02/21/2025
There is response from Bajaj infra Team
This updated is communicated with Rubiscape interal stackholder i.e. Sheetal G. anf Niranjan Dixit.
no updated received from them till
Putting this task as completed and mark this project/deployment on hold
Actions